Under 1919.73(a), when must unit proof tests of derricks be carried out?
Under 1919.73(a) unit proof tests of derricks must be carried out at the same times specified for cranes in 1919.71(a).
- These test intervals are set by the crane inspection and testing schedule referenced in 1919.71(a).
- Always document the test date and link it to the crane/derrick schedule required by 1919.71.
(See 1919.73(a).)