OSHA AI Agent
Get instant answers to any safety question.
Request Demo
OSHA 1926.753

Hoisting and rigging requirements

Subpart R

24 Questions & Answers
10 Interpretations

Questions & Answers

Under 1926.753(a), which provisions of the hoisting and rigging rules apply to steel erection cranes and which specific subsection is excluded?

All the hoisting and rigging provisions of Subpart CC apply to hoisting and rigging used in steel erection, except that 1926.1431(a) is excluded from application under steel erection activities. See 1926.753(a).

Under 1926.753(c)(1), who must perform the pre-shift visual inspection of cranes used in steel erection and what is the basic scope?

A competent person must visually inspect cranes prior to each shift and observe for deficiencies during operation. See 1926.753(c)(1).

  • "Competent person" is responsible for the inspection and must look for deficiencies while the crane is operating.
  • The inspection is a visual pre-shift check to identify items listed in 1926.753(c)(1)(i).

Under 1926.753(c)(1)(i), what specific crane components must be checked at a minimum during the pre-shift inspection?

At a minimum, the competent person must inspect controls, drive mechanisms, safety devices, pressurized lines, hooks and latches, wire rope reeving, electrical apparatus, hydraulic fluid level, tires, ground conditions, and level position of the hoisting equipment. See 1926.753(c)(1)(i).

Under 1926.753(c)(1)(ii)–(iii), what must be done if a pre-shift inspection finds a deficiency on a crane?

If a deficiency is found, the competent person must immediately determine whether it constitutes a hazard, and if it does, the hoisting equipment must be removed from service until corrected. See 1926.753(c)(1)(ii) and 1926.753(c)(1)(iii).

  • If the deficiency is not a hazard, the competent person still documents or monitors it per site procedures.
  • If it is a hazard, stop using the equipment immediately until repairs or corrective actions are completed.

Under 1926.753(c)(1)(iv), what authority does the crane operator have during operations if they have safety doubts?

The crane operator is responsible for operations under their direct control and has the authority to stop work and refuse to handle loads whenever there is any doubt about safety. See 1926.753(c)(1)(iv).

  • This gives operators immediate stop-work authority to prevent unsafe lifts or conditions.
  • Employers should support operators who stop work for safety reasons.

Under 1926.753(c)(2), who must inspect rigging prior to each shift and what standard governs that inspection?

A qualified rigger (a rigger who is also a qualified person) must inspect rigging prior to each shift in accordance with [1926.251]. See 1926.753(c)(2) and 1926.251.

  • Use 1926.251 to determine specific rigging inspection items and frequency.

Under 1926.753(c)(3)–(4), may the hoist hook or headache ball be used to lift personnel during steel erection?

No, the headache ball, hook, or load must not be used to transport personnel, except when cranes or derricks hoist employees on a personnel platform that meets all of [1926.1431] requirements (except for [1926.1431(a)] which is excluded). See 1926.753(c)(3) and 1926.753(c)(4).

  • If using a personnel platform, the employer must comply with 1926.1431 requirements except for 1926.1431(a), which is excluded under steel erection per 1926.753(a).

Under 1926.753(c)(5), when may safety latches on hooks be deactivated during steel erection?

Safety latches on hooks may only be deactivated when a qualified rigger determines that removing the latch makes hoisting and placing purlins and single joists safer, or when equivalent protection is provided in a site-specific erection plan. See 1926.753(c)(5), 1926.753(c)(5)(i), and 1926.753(c)(5)(ii).

  • Deactivation is strictly limited and must be based on a qualified rigger's determination or a documented site-specific plan that offers equivalent safety.

Under 1926.753(d)(1), what planning is required for routes of suspended loads to protect employees?

Routes for suspended loads must be pre-planned so no employee is required to work directly below a suspended load, except those engaged in initial connection of steel or employees necessary for hooking/unhooking the load. See 1926.753(d)(1) and the exceptions in 1926.753(d)(1)(i) and 1926.753(d)(1)(ii).

  • Pre-planning should identify travel paths, exclusion zones, and communication to workers to avoid being under suspended loads.

Under 1926.753(d)(2), what requirements must be met when employees are working under suspended loads?

When working under suspended loads, materials must be rigged to prevent unintentional displacement, hooks with self-closing safety latches or equivalents must be used, and all loads must be rigged by a qualified rigger. See 1926.753(d)(2) and its subsections 1926.753(d)(2)(i), 1926.753(d)(2)(ii), and 1926.753(d)(2)(iii).

  • Ensure rigging prevents slips or sideways movement, use latches, and have qualified riggers perform the rigging.

Under 1926.753(e)(1), what are the criteria to perform a multiple lift in steel erection?

A multiple lift is allowed only if a multiple lift rigging assembly is used, no more than five members are hoisted per lift, only beams and similar structural members are lifted, all employees involved have training per [1926.761(c)(1)], and the crane manufacturer's specifications do not forbid the multiple lift. See 1926.753(e)(1), 1926.753(e)(1)(ii), 1926.753(e)(1)(iv), and 1926.753(e)(1)(v).

Under 1926.753(e)(2) and (3), how must multiple lift rigging assemblies be rated and what load limits apply?

Components of a multiple lift rigging assembly must be specifically designed and assembled with a certified maximum capacity for the total assembly and each attachment point, and the total load must not exceed the crane's rated capacity or the rigging capacity specified in the rigging rating chart. See 1926.753(e)(2), 1926.753(e)(3)(i), and 1926.753(e)(3)(ii).

  • Certification of capacity must be by the manufacturer or a qualified rigger (see 1926.753(e)).

Under 1926.753(e) what safety factor is required when certifying multiple lift rigging assembly component capacity?

The certified capacity must be based on the manufacturer's specifications with a 5 to 1 safety factor for all components. See 1926.753(e).

  • Certification may be provided by the manufacturer or a qualified rigger as stated in the standard.

Under 1926.753(e)(4)–(6), how must members be rigged and set in a multiple lift assembly?

Members in a multiple lift must be attached at their center of gravity and kept reasonably level, rigged from top down, rigged at least 7 feet apart, then set from the bottom up, and controlled load lowering must be used whenever the load is over the connectors. See 1926.753(e)(4), 1926.753(e)(5), and 1926.753(e)(6).

  • Maintain spacing of at least 7 feet (2.1 m) between members and rig so each is level about its center of gravity.

Under 1926.753(c)(1)(i)(J) and (K), what ground and level checks are required for hoisting equipment?

The pre-shift inspection must include checking ground conditions for proper support (including settling, groundwater, or conditions around outriggers) and verifying the hoisting equipment is in a level position. See 1926.753(c)(1)(i)(J) and 1926.753(c)(1)(i)(K).

Under 1926.753(c)(1)(i)(F), how should wire rope be inspected during pre-shift checks?

Wire rope reeving must be inspected for compliance with the hoisting equipment manufacturer's specifications. See 1926.753(c)(1)(i)(F).

  • Inspect for fraying, broken wires, corrosion, kinking, or other defects as specified by the manufacturer's guidance and repair/replace if outside allowable limits.

Under 1926.753(e)(1)(iv) and 1926.761(c)(1), who must be trained for multiple lifts and what training is referenced?

All employees engaged in a multiple lift must be trained in the multiple lift procedures in accordance with [1926.761(c)(1)]. See 1926.753(e)(1)(iv) and 1926.761(c)(1).

  • Training should cover the rigging assembly, signals, hazards, and safe procedures for performing multiple lifts as required by the referenced training provision.

Under 1926.753(d)(2)(ii), can hooks without self-closing safety latches be used when employees must work under suspended loads?

No, hooks with self-closing safety latches or an equivalent means to prevent components from slipping out must be used when working under suspended loads. See 1926.753(d)(2)(ii).

  • The only exceptions are when a qualified rigger deactivates the latch per 1926.753(c)(5) for specific operations with equivalent protection.

Under 1926.753(c)(5)(i), when a qualified rigger deactivates a safety latch for placing purlins and single joists, what must justify that action?

The qualified rigger must determine that hoisting and placing purlins and single joists can be performed more safely by deactivating the safety latch. See 1926.753(c)(5)(i).

  • The determination should be documented or evident from the rigging plan and alternative protections must be in place to prevent unintentional disengagement.

Under 1926.753(e)(3)(i) and (ii), how do you determine whether a multiple lift's total load is acceptable?

Ensure the total load does not exceed the hoisting equipment's rated capacity from the equipment load charts and does not exceed the rigging capacity specified in the rigging rating chart. See 1926.753(e)(3)(i) and 1926.753(e)(3)(ii).

  • Verify both the crane load chart and the rigging chart before performing the lift, and account for load geometry and sling angles when calculating applied loads.

Under 1926.753(c)(1)(i)(G) and (H), what electrical and hydraulic checks are required in the pre-shift inspection?

The competent person must check electrical apparatus for malfunction, deterioration, dirt, or moisture accumulation and verify hydraulic systems have proper fluid level. See 1926.753(c)(1)(i)(G) and 1926.753(c)(1)(i)(H).

  • Correct or remove from service any electrical or hydraulic deficiencies that constitute a hazard as required by 1926.753(c)(1)(ii)–(iii).

Under 1926.753(c)(1)(i)(I), what must be checked about crane tires during the pre-shift inspection?

Tires must be inspected for proper inflation and condition during the pre-shift inspection. See 1926.753(c)(1)(i)(I).

  • Check for cuts, bulges, excessive wear, and correct inflation pressure per the equipment manufacturer's recommendations.

Under 1926.753(e)(4)(ii)–(iii), how should rigging be assembled for multiple lifts in terms of direction and spacing?

The multiple lift rigging assembly must be rigged from the top down and members must be rigged at least 7 feet (2.1 m) apart. See 1926.753(e)(4)(ii) and 1926.753(e)(4)(iii).

  • Maintain the spacing to reduce interaction between members and keep them reasonably level per 1926.753(e)(4)(i).

Under 1926.753, where can employers find requirements governing personnel platforms hoisted by cranes during steel erection?

Employers must meet all provisions of [1926.1431] (Cranes and Derricks — Personnel Platforms) except [1926.1431(a)], which is excluded under steel erection per [1926.753(a)]; see 1926.753(c)(4) and 1926.1431.